Blasting Overhangs Close to a Vibration Sensitive Structure
R.Farnfield Technical Services Manager, EPC-UK B.Williams Director of Commercial Operations, EPC-UK
Abstract
This paper describes a situation that many drilling and blasting
contractors have found themselves in - a client's fear of the use of
explosives.
In the summer of 2007 Blasting Services Ltd was asked to undertake some
drilling and blasting work in an abandoned quarry that was being
restored for a housing development. Previous quarrying operations had
left a series of overhangs that were considered unsafe and required
removing. The site contractor considered that the best and safest way
to carry out this work was by drilling and blasting. Blasting Services
Ltd, with the technical assistance of EPC-UK, designed a drilling and
blasting regime to accomplish this work with a series of trim blasts.
The design took into account the close proximity of a structure in very
poor condition and the imposed vibration limit of 6.0 mm/s. The faces
were profiled, holes drilled and explosives ordered. A few days before
the first blast was due to be carried out the client decided that the
poor condition of the nearby structure meant that the use of explosives
could not be permitted. This decision was made despite the blast design
indicating that the vibration level would be well below the 6.0 mm/s
limit.
Over the next few weeks a series of
unsuccessful trials were undertaken with alternative excavation
techniques. During this period no work was permitted on site due to the
unsafe condition of the faces and the cost to the client and main
contractor began to mount rapidly. Throughout this period Blasting
Services insisted that the best way to remove the overhangs was by the
controlled use of explosives. The client eventually agreed to go ahead
with the use of explosives but imposed an even more stringent vibration
limit of 4.0 mm/s. The original trim blast was redesigned to take into
account the new vibration limit giving a maximum instantaneous charge
weight of 2.5 kg and employing a combination of high-energy detonating
cord, dynamite and electronic detonators. Two trim blasts were
successfully fired with vibrations levels between 2.0 and 3.0 mm/s. The
building remained undamaged.
This paper describes the processes followed in undertaking this
drilling and blasting contract where the use of explosives was banned.